Bayshore Bikeway Status Update

Printer-friendly versionPrinter-friendly version

Judging from the above picture which shows the intersection at Bayshore & Main St., the Bayshore Bikeway Phase II Project is making considerable headway.  There are even cyclists using the striped bikelane already!

In the coming weeks, additional paving, striping, and installation of rumble strips will be completed.  After those punch list items are finished, a ribbon cutting ceremony will be held to officially dedicate Brisbane's newest bikelane.  Council will be setting the date of the ribbon cutting ceremony at their Sept. 19th meeting, so stay tuned for when the special event will be taking place.  For more information on the Bayshore Bikeway Phase II project, please click here.