Pavement Maintenance 2011

Printer-friendly versionPrinter-friendly version

As part of the City's annual Pavement Maintenance Project, all of Kings Rd., Annis between Humboldt and San Bruno, and the Alleys between Mariposa and Klamath will be re-paved.  The map below shows the demarcated streets (click to enlarge).

Work is being completed this year by Bortolotto and Co., which was awared the construction contract at the Oct. 17th City Council meeting.  Please note:

  • Grinding on Annis and the Alleys will be on Tuesday, Nov. 15th.  All cars need to be moved off the streets by 9:00am and may be returned after 4:00pm.
  • Grinding on Kings will take place on Wednesday., Nov. 16th.  All cars must be moved off the street by 9:00am and may be returned after 4:00pm.
  • Paving on Kings will take place Thursday - Friday, Nov. 17th and 18th and Monday, Nov. 21st.  All cars must be moved off the street by 9:00am and may be returned after 4:00pm Thursday and Friday.
  • Paving on Annis and the Alleys that was originally scheduled for Monday, Nov. 21st was completed on Wednesday, Nov. 16th (with all residences having been notified beforehand).
  • With garbage collection in these areas falling on either Thursday or Friday, the City is working with SSF Scavengers to have the garbage on the affected streets picked up prior to work starting at 9:00am (the streets being paved are too narrow for both the garbage truck and construction vehicles to fit simultaneously).
  • Flagmen will be present at the road closures on Kings, so please exercise caution when driving near the construction areas.
  • Striping will be scheduled after the asphalt has had time to properly cure.

Thank you in advance for your assistance in ensuring these streets are re-paved as safely and efficiently as possible!

(updated: 11/17/2011 @ 4:55pm)