On Saturday, July 16th, PG&E crews will be doing final connection of new pipeline within the Geneva Substation. As part of this work they will be venting natural gas to clear the line for welding to occur. The small natural gas release will occur around 2:00am at the corner of Geneva Avenue and Bayshore Boulevard. The release is only about 600 feet of pipe, so it should go quickly.
Depending on work progress later Saturday afternoon (between 3:00-6:00pm) the project team will purge the line to 100% natural gas in putting it into service. The PG&E team has made contact with the businesses in proximity to the work.
Scheduled Dates: Saturday, July 16, 2016
Work to be completed: Release of Natural Gas to Atmosphere
Approximate Time: 2:00am and between 3:00-6:00pm (depending on work progress)
Duration: 20 minutes, then 12-16 hours with air movers; 15 minutes for the purging
Location: Venting at Geneva Avenue and Bayshore Boulevard; Air Movers at Geneva and Bayshore Boulevard
We want to ensure you are provided with the most up-to-date information, but please note these times are subject to change.
Depending on the location of gas venting and weather patterns, there may be a smell of natural gas. The pipeline is cleared of gas utilizing a safe and common technique. As part of normal protocol, PG&E has and will continue to notify the appropriate public safety agencies, businesses and residents of this work. They are taking steps to mitigate noise and odor and have scheduled the work to create the least impact possible, however it is likely that the work will result in some noise and odor. The customer care team will be notifying customers in proximity to the release by automated calls this evening.
Safety is a top priority and PG&E encourages any resident who has questions or concerns about the smell of gas to call them 24 hours a day at 1-800-743-5000 or call 9-1-1 immediately.