UPDATED January 27, 2015 -

On Jan. 6th, skatepark design consultant Spohn Ranch held a Community Workshop to obtain feedback on design options they prepared for the proposed new Brisbane skatepark.  The majority of attendees preferred the layout that retained the existing skatepark footprint at Old County Road and Park Lane and added a few features at a “skate spot” in the small unused space west of the existing basketball courts (see Option 2 below).  Per the Council approved process, the Joint Council Facilities and Parks and Recreation Teen Services Subcommittee will recommend one option and a financing plan to the City Council. If approved, the Council will next authorize the development of plans and specifications for bidding by contractors.  Staff will ensure that the community gets an opportunity to weigh in on the actual design when it comes to fruition.  Look for the skatepark design to be on an upcoming Council meeting agenda.

* * * * *

At the January 6, 2014 Skatepark Community Workshop at City Hall (start time: 5:00pm), conceptual design consultant Spohn Ranch will be presenting the following three proposed options for the skatepark at its existing site.  Below are 3D plans for each, along with a labeled diagram of Option 1 and one for Option 2's "skate spot", as the elements are repeated in the different options.  Note: each of the images are clickable to be viewed larger.

[1]

OPTION 1 – Existing Footprint

Cost = $200,000
Area = 5,225 Sq. ft. +/-
Pros:  Least expensive option; doesn’t impact basketball courts
Cons:  Smaller total area than Options 2 or 3

[2]

 

[3]

OPTION 2 – Existing Footprint plus Skate Spot at Park Place

Cost = $250,000
Area = 6,400 Sq. ft. +/-
Pros:  Two unique spaces for skaters; doesn’t impact basketball courts; could do work in phases
Cons:  Cost is higher than Option 1

[4]


[5]

OPTION 3 – Single Larger Footprint (shift basketball court west)

Cost = $250,000
Area = 6,000 Sq. ft. +/-
Pros:  Provides one contiguous space for skaters
Cons:  Cost is higher than Option 1; disrupts basketball court use during relocation

Remember, the Skatepark Community Workshop takes place Tuesday, January 6, 2015 at 5 p.m. at the Community Meeting Room of Brisbane City Hall.  The consultant will also have 3D models of different elements that can be used to consider other configurations.  Lastly, if you haven't already done so, request to join the "Brisbane Skatepark" group on Facebook, which Spohn Ranch has set up to help gather design feedback from the Community: https://www.facebook.com/groups/brisbaneskatepark/ [6].

Submitted by City of Brisbane on December 24, 2014, 10:14 am
Powered by Drupal

Source URL:/news/2015-01-30/proposed-skatepark-options

Links
[1] /sites/default/files/Option 1 3D.pdf [2] /sites/default/files/Option 1 Labeled.pdf [3] /sites/default/files/Option 2 3D.pdf [4] /sites/default/files/Option 2 Labeled.pdf [5] /sites/default/files/Option 3 3D.pdf [6] https://www.facebook.com/groups/brisbaneskatepark/