UPDATE - Thursday, February 26, 2015: The contractors filled the main lap pool and kiddie/wading pool with water on Tuesday. The contractor will
brush the bottom and sides of the pool for several days as part of the curing process for the new plaster. They will be able to start up the heating system for the main lap pool tomorrow, and once it passes the County Health Dept inspection, it will be ready to open first thing Monday at 6:30am for lap swimming! View the Pool's Spring Schedule here: /community-pool The kiddie/wading pool will re-open a couple weeks after once proper maintenance on the controller and the system that maintains proper chemical balance is achieved.
UPDATE - Tuesday, February 24, 2015: Plaster is being set now in both the kiddie and main swimming pool. After it's been applied, it needs to cure and be swept for a few days to get residual material off. The Pool is still set to re-open on Monday, March 2, 2015!
UPDATE - Friday, February 6, 2015: Concrete for the pool deck was poured on Thursday. In the below photo you can see the worker providing a "broomed" finish. A broomed finish is considered an optimal finish for a pool deck in that it's not too smooth and slippery, nor too rough. The Pool is still on track to re-open March 2nd!
UPDATE - Tuesday, January 27, 2015: Retiling work going on at the Pool today...that means new lane markers and targets inside the pool and depth markers and No Diving graphics on the deck.
UPDATE - Friday, January 16, 2015: As of Wednesday evening the 14th, all the significant jackhammering needed for pool plaster removal work was completed. Next week's concrete deck removal work will be significantly less noisy. Thank you for your patience as this work is being completed.
UPDATE - Thursday, January 8, 2015:
Removal of the plaster and tile is going to start next week and will generate some noise. Working hours are 8 am to 5 pm. The work on removal of concrete deck sections containing rusted rebar should begin the following week.Starting in January 2015, the City plans to close the Community Pool [1] for approximately 6-8 weeks so that restoration work can be completed. That includes first draining the pool so that resurfacing, replastering, and re-tiling the pool floor can occur. Crews will also be performing a complete restoration of the pool's concrete deck to take care of the rusting rebar. At this time they'll also repair deck drain lines to ensure all of the inlets drain properly. The men's locker room tiles that are damaged will also be repaired during the closure, like the women's was in June of this year. Lastly, the kiddie pool which has not been operated in recent years due to problems keeping chlorine levels balanced, will in the coming weeks be tested to see if it can be operational after the closure. Public Works crews as well as pool maintenance support will take off the cover and get it running so that testing can be performed. All of this work was approved by the City Council on June 19, 2014 when the City's 2014/15 budget was adopted. The capital improvements that will be made to the Pool will help the City save money from there being less unscheduled repairs and closures in the future. The City is well-aware of the loyal patrons who use the Pool, even during the winter months, and asks for everyone's patience during the closure. Crews will work as diligently as possible to ensure the Pool reopens as soon as the restoration work has been completed. For any questions about this project, please contact the Public Works Department at (415) 508-2130.